Jammu & Kashmir

Delay in Srinagar-Leh power line project led to Rs 700 crore loss: CAG

Power grid. [File Photo]

Leads to cost escalation, extra expenditure of Rs 700 crore

Srinagar: The Comptroller and Auditor General of India has slammed the authorities over the delay in taking a decision for the construction of Srinagar-Leh transmission line, saying it not only led to a huge cost escalation but also caused a generation loss of 1,602.64 MUs and an extra expenditure of Rs 700.25 crore due to billing of deemed generation to Power Development Department.

In its report, the CAG has revealed that delay in taking decision over the construction of the transmission line caused huge financial losses.

“Due to the delay in taking a decision for construction of the line, not only huge cost escalation had occurred but there was also a generation loss of 1,602.64 MUs and an extra expenditure of Rs 700. 25 crore due to billing of deemed generation to Power Development Department,” reads the CAG’s compliance audit of activities selected Central Public Sector Enterprises.

In 2003, the Government of India announced a special package for JK comprising a 375 km transmission system project from Srinagar to Leh via Kargil with four substations at Drass, Kargil, Leh and Khaltsi at an estimated cost of Rs 377.52 crore.

However, in September 2004, the scope of the transmission system was revised by shifting the overhead line between Gagangir to Zojila Pass to an underground line along with a change in the transmission capacity at Kargil sub-station, being an avalanche-prone area, which led to an increase in estimated cost to ₹633.79 crore,” reads the report.

On December 15, 2004, the Government of Jammu and Kashmir accorded its approval for execution of the project by Power Grid Corporation of India Limited (PGCIL); however, the project was put on hold by the Ministry of Power on June 27, 2005.

The project was finally approved by the Government of India in January 2014 at an estimated cost of Rs 1,788.41 crore with a scheduled completion period of 42 months from the date of release of the first installment of funds. The first installment was received on March 01, 2014, and the approved commissioning schedule of the project was September 2017.

The project was planned and implemented by PDD and commissioned in January 2019 with a delay of 16 months from the scheduled date.

The CAG has said that due to the time lag in the approval/ implementation of the transmission system, the completion cost has escalated to Rs 1,583.36 crore from the initial estimated cost of Rs 633.79 crore.

The audit further noticed that in the absence of national grid connectivity due to a delay in the commissioning of Srinagar -Leh transmission system, Chutak and Nimmo Bazgo hydropower stations were operated in isolation mode and could not be optimally utilized upto their designed capacity and their generation had to be curtailed up to the limited requirements of the Ladakh region only. “As a result, 1,602.64 MUs of power could not be generated which resulted in generation loss,” the report states.

According to the report, NHPC raised a bill of Rs 1,166.56 crore for deemed generation from these two projects on the Power Development Department.

“Actual generation from these two power stations was only 736.75 MUs (29 percent) against their generation capacity of 2,524.36 MUs.

The Central Electricity Regulatory Commission, however, allowed NHPC to claim the tariff in respect of deemed generation. Accordingly, NHPC raised a bill of RS 1,166.56 crore for deemed generation on Power Development Department (J&K) and received part payment of ₹267.59 crore from the Power Development Department and the balance amount is yet to be paid,” the report states.

 